Two travel lanes will be maintained in both the northbound and southbound direction. Traffic will be controlled by temporary barriers.
Now, starting on or after Tuesday, May 30, the I-65 northbound exit ramp and entrance ramp at State Road 47 will close. It’s expected to reopen after the end of December.
This contract was awarded to E & B Paving, LLC for over $83.7 million. It also includes bridge replacements near U.S. 52, a bridge removal near Lafayette Avenue, culvert work and drainage construction on I-65. The entire project is expected to be completed in December of 2023.